Data centre land developer Tract has unveiled plans to build a 500MW AI data centre campus across seven buildings in County Durham. The company announced the project on 3 November 2026, marking its formal expansion into the UK market as it begins seeking public feedback on the proposal.
Key points
- Tract has proposed a 500MW data centre development in County Durham across seven dedicated facilities.
- The project marks the developer’s first entry into the United Kingdom infrastructure sector.
- The company is gathering community and industry feedback before moving forward through local planning stages.
The County Durham proposal
Data Center Dynamics reported that Tract has entered the UK development pipeline with proposals for a multi-facility site in North East England. The master plan calls for seven individual buildings delivering up to 500 megawatts of IT capacity once fully built out.
The company has opened a consultation process to gather feedback from local stakeholders and residents. Securing early feedback allows developers to address environmental considerations, transport links, and utility connections before submitting detailed planning applications to local planning authorities.
Building out a 500MW campus represents one of the largest single development envelopes put forward in the region. Modern artificial intelligence clusters require dedicated facilities designed to supply dense rack configurations, advanced cooling systems, and massive electrical switchgear.
Expanding into the British market
The Durham project marks Tract’s first public venture into the UK. The firm specialises in identifying land, securing power reservations, and preparing industrial campuses so that hyperscale cloud companies and artificial intelligence operators can deploy capacity without navigating multi-year zoning delays.
Britain has become a prime target for international infrastructure investment. Rising demand for machine learning clusters has led operators to look beyond the crowded Slough and London corridor, where power availability remains constrained and land prices remain high.
The move mirrors wider activity across northern England. Energy developers and investment firms have increasingly targeted former industrial and energy generation sites, such as the Drax AI data centre planned in a £20bn Brookfield deal in Yorkshire. Northern locations offer access to offshore wind transmission lines coming ashore from the North Sea, making them attractive for high-draw facilities.
Meeting rising AI power requirements
A capacity of 500 megawatts places the planned Durham site on par with major international compute hubs. Running modern frontier training runs and dense inference deployments demands continuous electricity supplies that dwarf conventional enterprise workloads.
The scale reflects an industry-wide pivot toward centralised mega-campuses. Major model developers have adjusted their procurement strategies to secure dedicated grid connections, visible in broader industry plans for dedicated AI compute campuses designed from the ground up to host specialised accelerators.
Distributing this level of electricity inside server halls has also required engineering adjustments across the supply chain. Operators are adopting higher voltage power architectures and direct liquid cooling loops to prevent thermal throttling. Recent industrial trials have shown that adopting direct current distribution for AI facilities can lower transmission losses within multi-hundred-megawatt sites.
What happens next
Tract will compile feedback from its initial public consultation before finalising planning documents for Durham County Council. The timeline for formal planning submission, ground breaking, and phased energisation has not yet been published.
Any formal planning application will require detailed grid impact assessments with National Grid ESO. The speed of approval and grid connection agreements will determine when the seven planned buildings can welcome their first tenant equipment.